| Services | Timeline |
|---|---|
| Tree Transit Permit ( Including Tree Felling NOC ) | 42 days |
| Tree Felling & Tree Transit | 25 days |
| Joint Verification Uploading | 4 + 5 days |
| Approved Property Hammer | 4 days |
| TT Permit Issued | 4 days |
| Services | No. of Applications Received | No. of Applications Approved | Minimum Time taken for the application | Maximum Time taken for the application | Median Time taken for the application | Average Time taken for the application | Average Fee Paid |
|---|---|---|---|---|---|---|---|
| Tree Felling & Tree Transit | 2627 | 387 | 4 Days | 509 Days | 125 Days | 83 Days | No fees charged |
| Joint Verification Uploading | 602 | 532 | 0 Days | 326 Days | 3 Days | 14 Days | No fees charged |
| Approved Property Hammer | 271 | 209 | 0 Days | 252 Days | 23 Days | 32 Days | No fees charged |
| TT Permit Issued | 255 | 94 | 29 Days | 543 Days | 182 Days | 218 Days | No fees charged |