Services | Timeline |
---|---|
Tree Transit Permit ( Including Tree Felling NOC ) | 42 days |
Tree Felling & Tree Transit | 25 days |
Joint Verification Uploading | 4 + 5 days |
Approved Property Hammer | 4 days |
TT Permit Issued | 4 days |
Services | No. of Applications Received | No. of Applications Approved | Minimum Time taken for the application | Maximum Time taken for the application | Median Time taken for the application | Average Time taken for the application | Average Fee Paid |
---|---|---|---|---|---|---|---|
Tree Felling & Tree Transit | 1955 | 236 | 6 Days | 346 Days | 101 Days | 73 Days | No fees charged |
Joint Verification Uploading | 412 | 380 | 0 Days | 296 Days | 2 Days | 12 Days | No fees charged |
Approved Property Hammer | 200 | 147 | 0 Days | 252 Days | 22 Days | 32 Days | No fees charged |
TT Permit Issued | 175 | 42 | 54 Days | 429 Days | 213 Days | 206 Days | No fees charged |